Preventive maintenance plan to increase the availability of heavy fleet equipment at the Juvier S.A.C. concrete plant                                                                                                                                                                                                                                                                                                 preventive maintenance plan to increase the availability of heavy fleet equipment at the Juvier S.A.C. concrete plant

DOI: https://doi.org/10.22490/25394088.9992
Ashley Murillo Fernandez Cesar Vallejo University image/svg+xml
Buscal Kinosita Pierina Lisett Cesar Vallejo University image/svg+xml

This research contributes to Sustainable Development Goal (SDG) 9: Promote efficiency and sustainability in the industrial sector, as well as to guarantee equitable access to infrastructure. Its main objective was to develop a preventive maintenance plan to increase equipment availability at the JUVIER S.A.C. concrete plant. The investigation is an applied type, with a quantitative approach and

 

an experimental design. The sample consisted of eight heavy equipment at the concrete plant. Document review was used as a technique based on information collected at the company. Among the main findings, is highlighted that the availability percentage before the implementation of preventive maintenance was 86.95%. However, after its implementation, it increased to 95.97%, representing a 9.02%. improvement. The budget allocated for maintenance execution, based on the activity schedule for one month, was S/.13,406.88, and the total cost for the three months was S/. 40220.64. In conclusion, the results indicated that, by implementing the preventive maintenance plan, equipment availability increased significantly, thus confirming the effectiveness of preventive maintenance in equipment operation.

keywords: availability, equipment, maintenance
license

How to Cite

Murillo Fernandez, A., & Buscal Kinosita , P. L. (2025). Preventive maintenance plan to increase the availability of heavy fleet equipment at the Juvier S.A.C. concrete plant                                                                                                                                                                                                                                                                                                 preventive maintenance plan to increase the availability of heavy fleet equipment at the Juvier S.A.C. concrete plant. Publicaciones E Investigación, 19(2). https://doi.org/10.22490/25394088.9992
Almétricas

PRIVACY STATEMENT: In accordance with the Personal Data Protection Law (Law 1581 of 2012), the names and email addresses managed by Publicaciones e Investigación will be used exclusively for the purposes stated by this journal and will not be made available for any other purpose or to any other individual. Manuscripts submitted to the publication are only accessible to the editorial team and external peer reviewers. 